Working in MUD 12

Mud 12 Board meeting was held on Monday, September 16, 2019. Two main items discussed were the tax rate and the fine screen for the plant. The tax rate which was proposed at the last meeting was voted on and passed by the Board. The new tax rate lowered the previous rate from .2395 to.2230/$100 […]

Wastewater Treatment Plant Rehabilitation Project Update #10

Wastewater work continues close to schedule. The temporary tanks have been installed and the valves placed to transfer incoming flow into temporary tanks. These tanks are now taking the flow and our aeration tanks are now offline and beginning to be cleaned. Also the base for the new fine screen has been poured. Cleaning and […]

Wastewater Treatment Plant Rehabilitation Project Update #9

Mud 12 Residents The Wastewater plant is progressing close to schedule. Currently the temporary tanks are online at Galveston MUD 12 and flow is going to the clarifier. This means the flow into existing aeration tanks has ceased so the clean-out and repair can start. Existing aeration tanks, clarifiers and new fine screen are the […]