July 18, 2019

Wastewater Treatment Plant Rehabilitation Project Update #11

July Report- *The new mechanical fine screen was placed on the headworks deck and piping started. *The new screen's control...
Read More
May 7, 2019 / Newsletter

Wastewater Treatment Plant Rehabilitation Project Update #10

Wastewater work continues close to schedule. The temporary tanks have been installed and the valves placed to transfer incoming flow...
Read More
April 18, 2019 / Newsletter

Wastewater Treatment Plant Rehabilitation Project Update #9

Mud 12 Residents The Wastewater plant is progressing close to schedule. Currently the temporary tanks are online at Galveston MUD...
Read More