Wastewater Treatment Plant Rehabilitation Project Update-01

Jan 7, 2018. Received a project format with dates of completion for phases.

Work started last week with uncovering pipes from Aeration to clarifer. These pipes were uncovered and slope was recorded.

Checked status on new pipe and they has arrived storage yard.

All systems go.